Rural New-Build Foundations - Sturmer
Private homeowner
Approx. 3-4 weeks
Project Overview
Groundworks and foundation preparation for a rural new-build in Sturmer, Essex. The works included trench foundations and reinforced slab preparation to form a stable base for the new home.
The Challenge
The rural site required bulk excavation and careful sequencing to manage spoil, maintain access, and keep the foundation layout accurate across the footprint.
Our Solution
We excavated trench foundations, set levels, and prepared a reinforced slab with membrane protection. The works were sequenced to keep the footprint clean and ready for the concrete pour.
Results & Outcome
A completed foundation platform was delivered, ready for the superstructure and follow-on build stages.
Technical Specifications
Project Gallery









Related Projects

Complete groundworks and CFA piling for a two-storey rear extension on a Victorian property. The project included foundation design, piling works, ground beams, and drainage installation.
View Project
Complete foundation package for a mixed-use development including basement excavation, piling works, ground beams, pile caps, drainage systems, and hard landscaping.
View ProjectStart Your Project
Get expert foundation solutions for your project. Contact us for a free consultation and quote.